How we build

From plot to keys: how building with ASSA works

Building a house involves several parties: the architect, the câmara, the bank and the builder. Here is the order, who does what and what you bring.

Durations below come from public sources or are still to be confirmed S‑3. 12⁠–⁠24 months from plot to keys is common (Santander). At ASSA, contract to keys for a 150 to 220 m² house: 18 to 24 months.

Night-time axonometric of the finished house with points 1 to 4 numbered: cantilever, covered terrace, pool and garage.
Schematic drawing. Not an ASSA project.

Six steps from plot to keys

  1. Plot check and estimate

    What happens
    We look at the PDM, access, utilities and slope. You receive a cost range.
    Who
    ASSA
    Duration
    Days
    What you bring
    Caderneta predial, certidão, location plan
  2. Architecture and specialty projects

    What happens
    Architecture and specialty projects: structure, water, electricity, thermal.
    Who
    Your architect or one we work with S‑11
    Duration
    2⁠–⁠4 months S‑3
    What you bring
    The house brief: bedrooms, area, budget
  3. Licensing with the câmara

    What happens
    Filing with the câmara and following the process. DL 108/2026 changed the rules; we check your case.
    Who
    The architect, with the câmara
    Duration
    Varies by câmara
    What you bring
    Power of attorney, if you cannot sign
  4. Quote and contract

    What happens
    With the project and bill of quantities we send the quote. The terms are agreed in the contract.
    Who
    ASSA and the owner
    Duration
    S‑5 working days for the quote
    What you bring
    Approved project and bill of quantities
  5. Build

    What happens
    Foundations, structure, roof, services and finishes.
    Who
    ASSA, with IMPIC alvará and liability insurance
    Duration
    18 to 24 months, contract to keys (150 to 220 m²)
    What you bring
    Site visits whenever you like S‑7
  6. Handover and warranty

    What happens
    Final inspection, snag fixing and handover of the keys. By law, the builder is liable for defects in the work for 5 years from handover (Portuguese Civil Code, art. 1225).
    Who
    ASSA and the client
    Duration
    Days
    What you bring
    The inspection checklist

Payment by stages

You pay in three instalments, each after a signed record of the work completed. The total price and the deadline are in the contract. Which construction stages each instalment covers: S‑7.

InstalmentShareWhen it is paid
1st instalment40%After the signed record of work completed
2nd instalment40%After the signed record of work completed
3rd instalment20%After the signed record of work completed

Construction credit

With a construction loan the bank releases money in 3 to 6 tranches, against progress on site (autos de medição). It is slower and needs more paperwork than a purchase loan.

What can go wrong

  1. Changes in scope

    New requests halfway through change the price and timing. They are agreed separately and go ahead only on a priced estimate.

  2. Weather

    Prolonged rain delays foundations and roofing. We tell you in writing and adjust the plan.

  3. Licence delays

    They depend on the câmara. We tell you what is pending and from whom.

Let’s start with your plot

Where are you now?

Tell us where you are, and we will tell you the next step.

Free, no obligation. S‑13

After your request, Sergii calls you within S‑5 · N working hours.

Drawing of a 28 by 20 metre plot with the house footprint